Walls without Headers Syracuse NY

The walls in Syracuse were probably built using a concealed header at every sixth course in a bonding pattern known as a diagonal or herring-bone. These diagonal or herring-bone headers consist of brick units that were installed at an angle, as shown in Fig. 1. The corners of the units in the face brick stretcher course are clipped off to accommodate this diagonal unit.

Landscapes East, Inc.
(315) 682-9044
8012 Saintsville Rd.
Kirkville, NY

Data Provided by:
Kozscapes Landscaping
(315) 445-2450
114 Somerset Rd
Syracuse, NY
 
Edward M Basta Landscape Architect
(315) 425-0179
136 Walton St # 1
Syracuse, NY
 
Maxian & Horst
(315) 472-2461
306 Hawley Ave
Syracuse, NY
 
Hanley Landscaping & Lawncare
(315) 491-9669
1120 Teall Ave
Syracuse, NY
 
Jeff's Lawn & Landscaping
(315) 475-8527
404 Scoville Ave
Syracuse, NY
 
Montes Landscaping
(315) 952-8211
Syracuse, NY
 
Simply Reliable Landscaping
(315) 479-8776
413 Dewitt St
Syracuse, NY
 
Blessed Landscaping Hauling & Plowing Services
(315) 478-0492
Syracuse, NY
 
Osier Landscaping & Construction Incorporated
(315) 463-5600
110 Arterial Rd
Syracuse, NY
 
Data Provided by:

Walls without Headers

Provided By:

Source: MASONRY CONSTRUCTION MAGAZINE
Publication date: September 1, 2005

I have seen several older masonry walls that have the appearance of running bond, yet do not contain any visible headers. In going over the walls with a metal detector, there is no indication of any wall ties.

Were these walls built without headers or ties?

The walls were probably built using a concealed header at every sixth course in a bonding pattern known as a diagonal or herring-bone. These diagonal or herring-bone headers consist of brick units that were installed at an angle, as shown in Fig. 1. The corners of the units in the face brick stretcher course are clipped off to accommodate this diagonal unit.

Another method for concealing headers involves splitting the face brick in half and then backing these split-face brick with a continuous row of header occurring every sixth course throughout the height of the wall, as shown in Fig. 2.

These methods are described in the book Masonry Carpentry Joinery - The Art of Architecture, Engineering and Construction in 1899 published by Chicago Review Press, which contains selections from the International Library of Technology published by the International Textbook Co., Scranton, Pa., in 1899.

In both methods the headers are held in by the mortar bond of the bed joint for the stretcher courses above and below the diagonal header or concealed perpendicular header. Because the headers are not visible on the exterior face of the wall.